Malpas Parish Council has received the following update from the area CWaC Highways engineer.
Thank you for your email.
Apologies that my response is so close to your meeting start.
Church Street
My understanding is we are still on course to commence the temporary propping in early July.
Bradley Bridge
As you will be aware works have commenced and remain on schedule for completion by the end of the week.
Other matters
Chester Road, Malpas – Pre-patching works are now planned for Friday 18th and Saturday 19th June after the bridge works on Bradley bridge are complete. Surface dressing of the road to follow provisionally starting Monday 28 June
I am also keen to improve our links and communication and I understand from Cllr Williams that a ward walk will be arranged for the Malpas area in the near future.
I look forward to discussing matters at the meeting.
However, in the intervening period if you require any other information on matters in Malpas moving forward, please let me know.